BERLIN - Britzer Damm
BERLIN - Congress hall Berlin
BERLIN - Mörschbridge
BERLIN - Sandkrug bridge
BERLIN - Suedostallee
BERLIN - Teltowkanal
BERLIN - Thaer street bridge
BERLIN - Tunnel Ortskern Britz
BREMEN - Overpass, A281
BRIESEN - Pedestrian bridge
DEGGENDORF - Danube bridge
DONAUSTAUF - Danube bridge
DUESSELDORF - Cable stayed bridges over railway tracks
DUESSELDORF - Rhine bridge family
DUESSELDORF - Subway construction
DUESSELDORF - Tunneling
EBERSWALDE - Kloster bridge
FINOWFURT - Eberswalde
FISCHERDORF - Danube bridge
Hamburg - 4th tube Elbe tunnel
HAMBURG - Flood protection structure
Hamburg - motorway cross Hamburg East
HAMBURG - Norderelbe bridge
HAMBURG - Suederelbe bridge
HAMBURG - Underpass Waltershofer Damm
HAMBURG - Viaduct Roedingsmarkt
HÄMERTEN - Elbe bridges
ITZEHOE Störbrücke
KAPPELN - Schlei bridge
MAGDEBURG - Waterways junction
METTLACH - Saar-Staustufe
MÜNCHEN - Isar bridge Gruenwald
REGENSBURG - Nibelungen bridge
RENDSBURG - Railway high bridge
STRALSUND - Greifswalder Chaussee
STRALSUND - Ziegelgrabenbridge
STRODEHNE - Havel bridge
TRANSRAPID
USEDOM - Underpass Bansin
WUPPERTAL - Suspension railway - column no. 100
 
Project
RENDSBURG - Railway high bridge over the North-Baltic Sea-Canal, built in 1913

Location
Germany, Rendsburg

Client
WSA Kiel-Holtenau

Services
Preliminary and detailed design, static and structural checking

Processing time
1990 - 1999

Kind of building
Railway bridge

Canal bridge
Overall length: 77.30 + 140.00 + 77.30 = ca. 295 m
Cross section: Two track trough bridge with open carriageway
System: Three span truss bridge: two side parts (L = 77.30 m) with trussed pylons as half frame and cantilevers (L = 26.20 m); one middle part (L = 87.60 m), supported on the cantilevers

Approach bridges
Overall length: About 2,117 m
Cross section: Two parallel suspended single track deck bridges with open carriage way
System: Solid web single span beams over 107 spans between abutments, supporting jacks and changeover columns and over supporting jacks and transition columns - length of span: 10 to 29 m

Loop bridge
Length: About 75 m
Cross section: Two-track deck bridges with open carriageway
System: Trussed framework

Supporting jacks, transition columns
Hight: About 19.50 to 33.50 m
System: 3-dimensional framework

Foundation
Flat foundation

Construction Method
Riveted steel sheet structure

Note
Static calculations and working drawings, design and call for tender for replacement of the canal bridge end-bearings and of the ramp bridge bearings. Independence checking of the static calculations and of the planing of the repair work



 