Viktoria Bridge in Bonn

Installation of 40 m prefabricated steel–concrete composite girders above ICE DB rail trac

In calendar week 51, seven prefabricated steel–concrete composite girders were installed during three night-time road and track closures, and seven girders were installed under traffic. During the traffic closures between 12:35 a.m. and 5:20 a.m., both the Viktoria Bridge and the rail tracks were closed.

The central girders of the western superstructure are 40 m long and were delivered from the precast concrete plant in Erfurt to Bonn by special transport. Each of the girders weighed roughly 45 metric tons. Each girder of the south-west end span weighed roughly 28 metric tons. They were installed by a crawler crane.

Seven further girders of the north-west end span will be installed at the end of January 2021.

GRASSL was commissioned by the city of Bonn to carry out the services of work phases 1 to 7.

Determination of the project requirements, preliminary and detailed design, application for planning permission, execution design, tender preparation, planning of the traffic infrastructure, consulting services during construction.

Further information about the project and its execution can be found at:

https://www.bonn.de/themen-entdecken/verkehr-mobilitaet/sanierung-viktoriabruecke.php