B51, Münster Bypass, Trough Structure Mauritz

  • Home
  • Projects
  • B51, Münster Bypass, Trough Structure Mauritz

Year of completion

In progress

Type of intervention

New construction

Contracting authority

Landesbetrieb Straßenbau NRW

Trough Structure Mauritz
Pedestrian Bridge Laerer Landweg
Pedestrian Bridge Pleistermühlenweg
Gantrie km 5+960km
Gantrie km 6+260km
Temporary Bridges

Location

Münster

Type of structure

Road trough

Construction method

Sealing slab and slurry wall construction method

Total length

900,00 m

Construction width

25,00 m

Construction material

Glas, reinforced concrete, steel

Architect

Dirk Gottfried

Services Grassl

Preliminary design, detailed design, preparation of tendering, conceptual design of traffic infrastructure